TEPCO to start installing cover over No. 1 reactor on June 27 - AJW by The Asahi Shimbun

Submitted by RIJS on
Item Description
Article in Asahi Japan Watch by The Asahi Shimbun. Tokyo Electric Power Co. on June 27 will begin installing via remote control a temporary cover over the No. 1 reactor building at its troubled Fukushima No. 1 nuclear power plant, the utility said June 14.
Translation Approval
Off
Media Type
Layer Type
Archive
Internet Archive
Geolocation
37.761, 140.473
Latitude
37.761
Longitude
140.473
Location
37.761,140.473
Media Creator Username
AZ
Media Creator Realname
AZ
Media Date Create
Retweet
Off
English Title
TEPCO to start installing cover over No. 1 reactor on June 27 - AJW by The Asahi Shimbun
English Description
Article in Asahi Japan Watch by The Asahi Shimbun. Tokyo Electric Power Co. on June 27 will begin installing via remote control a temporary cover over the No. 1 reactor building at its troubled Fukushima No. 1 nuclear power plant, the utility said June 14.
ID at Source
1487
old_tags_text
a:10:{i:0;s:6:"remote";i:1;s:10:"no workers";i:2;s:13:"asahi shimbun";i:3;s:12:"no.1 reactor";i:4;s:21:"radioactive emissions";i:5;s:17:"Fukushima Daiichi";i:6;s:13:"Nuclear power";i:7;s:21:"prevent radioactivity";i:8;s:5:"TEPCO";i:9;s:15:"temporary cover";}
old_attributes_text
Once | Page | asz25@cornell.edu | English|
Flagged for Internet Archive
Off
URI
http://wayback.archive-it.org/2438/20110301000000/http://ajw.asahi.com/article/0311disaster/fukushima/AJ201106151181
Attribution URI
http://wayback.archive-it.org/2438/20110301000000/http://ajw.asahi.com/article/0311disaster/fukushima/AJ201106151181