Fukushima Daini Nuclear Power Station Unit 1 power panel (P/C 1C-1) installation 1. Power panel (P/C 1C-1) carried in from the opening of the Reactor Building annex Photo taken on April 13, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Fukushima Daini Nuclear Power Station Unit 1 power panel (P/C 1C-1) installation 1. Power panel (P/C 1C-1) carried in from the opening of the Reactor Building annex Photo taken on April 13, 2012
Fukushima Daini Nuclear Power Station Unit 1 power panel (P/C 1C-1) installation 3. Moving the power panel (P/C 1C-1) after it’s lifted down Photo taken on April 13, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Fukushima Daini Nuclear Power Station Unit 1 power panel (P/C 1C-1) installation 3. Moving the power panel (P/C 1C-1) after it’s lifted down Photo taken on April 13, 2012
Fukushima Daini Nuclear Power Station Unit 1 power panel (P/C 1C-1) installation 2. Power panel (P/C 1C-1) carried down through the opening Photo taken on April 13, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Fukushima Daini Nuclear Power Station Unit 1 power panel (P/C 1C-1) installation 2. Power panel (P/C 1C-1) carried down through the opening Photo taken on April 13, 2012
Permanent installation of Unit 4 residual heat removal cooling system, residual heat removal cooling sea water system and emergency diesel generator cooling system Switching to the permanent cable for the electric motor of emergency diesel generator cooli Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Permanent installation of Unit 4 residual heat removal cooling system, residual heat removal cooling sea water system and emergency diesel generator cooling system Switching to the permanent cable for the electric motor of emergency diesel generator cooli
Permanent installation of Unit 4 residual heat removal cooling system, residual heat removal cooling sea water system and emergency diesel generator cooling system Switching to the permanent cable for the electric motor of residual heat removal cooling sy Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Permanent installation of Unit 4 residual heat removal cooling system, residual heat removal cooling sea water system and emergency diesel generator cooling system Switching to the permanent cable for the electric motor of residual heat removal cooling sy
Function check of the residual heat removal cooling sea water system (B system) 4. Function check after installation (Vibration measurement during the trial run) Photo taken on April 12, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Function check of the residual heat removal cooling sea water system (B system) 4. Function check after installation (Vibration measurement during the trial run) Photo taken on April 12, 2012
Function check of the residual heat removal cooling sea water system (B system) 3. Function check after installation (Temperature measurement during the trial run) Photo taken on April 12, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Function check of the residual heat removal cooling sea water system (B system) 3. Function check after installation (Temperature measurement during the trial run) Photo taken on April 12, 2012
Permanent installation of Unit 4 residual heat removal cooling system, residual heat removal cooling sea water system and emergency diesel generator cooling system Switching to the permanent cable for the electric motor of residual heat removal cooling sy Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Permanent installation of Unit 4 residual heat removal cooling system, residual heat removal cooling sea water system and emergency diesel generator cooling system Switching to the permanent cable for the electric motor of residual heat removal cooling sy
Progress Status of Fukushima Daini Nuclear Power Station Recovery Plan (Monthly Report; April 2012) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Progress Status of Fukushima Daini Nuclear Power Station Recovery Plan (Monthly Report; April 2012)
TEPCO Plant status of Fukushima Daini Nuclear Power Station (Appendix) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about TEPCO Plant status of Fukushima Daini Nuclear Power Station (Appendix)