National Report of JAPAN for the 6th Review Meeting; Joint Convention on the Safety of Spent Fuel Mamagement and on the Safety of Radioactive Waste Management Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about National Report of JAPAN for the 6th Review Meeting; Joint Convention on the Safety of Spent Fuel Mamagement and on the Safety of Radioactive Waste Management
Regarding the Evaluation of the Report on installing alternative cooling and clean-up systems (Circulation Cooling System) for Spent Fuel Pools of Units 1 and 4 at Fukushima Daiichi Nuclear Power Station, Tokyo Electric Power Co., Inc. Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Regarding the Evaluation of the Report on installing alternative cooling and clean-up systems (Circulation Cooling System) for Spent Fuel Pools of Units 1 and 4 at Fukushima Daiichi Nuclear Power Station, Tokyo Electric Power Co., Inc.
Cover installation for fuel removal at Unit 3 (Northwest side) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Cover installation for fuel removal at Unit 3 (Northwest side)
Spent fuel dry cask temporary storage facility (Attachment) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Spent fuel dry cask temporary storage facility (Attachment)
Spent fuel common pool, etc. (Attachment) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Spent fuel common pool, etc. (Attachment)
Fuel removal from the Spent Fuel Pool (Attachment) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Fuel removal from the Spent Fuel Pool (Attachment)
Additional report on the steel beam falling into Unit 3 Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station (Attachment) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Additional report on the steel beam falling into Unit 3 Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station (Attachment)
A Supplementary explanation added on the report on the steel beam falling into Unit 3 Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station in response to the additional directive document received from the Nuclear Regulation Authority Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about A Supplementary explanation added on the report on the steel beam falling into Unit 3 Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station in response to the additional directive document received from the Nuclear Regulation Authority
Alteration of Report with regards to installation of circulating cooling system of Spent Fuel Pool of Unit 1-4 of Fukushima Daiichi Nuclear Power Station (summary) (Appendix) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Alteration of Report with regards to installation of circulating cooling system of Spent Fuel Pool of Unit 1-4 of Fukushima Daiichi Nuclear Power Station (summary) (Appendix)
Alteration of Report to NISA with regards to installation of alternative cooling and purification system of Spent Fuel Pool of Unit 1-4 of Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Alteration of Report to NISA with regards to installation of alternative cooling and purification system of Spent Fuel Pool of Unit 1-4 of Fukushima Daiichi Nuclear Power Station