Liquid leakage in the desalting facility for the spent fuel pool in Unit 4 of Fukushima Daiichi Nuclear Power Station (occurred on November 8) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Liquid leakage in the desalting facility for the spent fuel pool in Unit 4 of Fukushima Daiichi Nuclear Power Station (occurred on November 8)
The NRA has received the revision of the report from TEPCO on its additional measures to the event that a steel beam fell into the spent fuel pool of Unit 3, Fukushima Daiichi Nuclear Power Station. (Nov 19, 2012) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about The NRA has received the revision of the report from TEPCO on its additional measures to the event that a steel beam fell into the spent fuel pool of Unit 3, Fukushima Daiichi Nuclear Power Station. (Nov 19, 2012)
General plan of the cover for fuel removal of Unit 4 in Fukushima Daiichi Nuclear Power Station (Attachment) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about General plan of the cover for fuel removal of Unit 4 in Fukushima Daiichi Nuclear Power Station (Attachment)
General Plan and Start of main work of the cover for Fuel Removal of Unit 4 in Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about General Plan and Start of main work of the cover for Fuel Removal of Unit 4 in Fukushima Daiichi Nuclear Power Station
Remotely Operated Vehicle (underwater exploration vehicle) [pictured on February 7, 2012] Provided by; Hitachi-GE Nuclear Energy, Ltd. Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Remotely Operated Vehicle (underwater exploration vehicle) [pictured on February 7, 2012] Provided by; Hitachi-GE Nuclear Energy, Ltd.
The crack of axle linkage casing at the overhead crane in the building of spent fuel common pool, Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about The crack of axle linkage casing at the overhead crane in the building of spent fuel common pool, Fukushima Daiichi Nuclear Power Station
Alternative water injection line to Unit 4 spent fuel pool Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Alternative water injection line to Unit 4 spent fuel pool
R/B, Unit 4, Fukushima Daiichi Nuclear Power Station Installation work of supporting structure at the bottom of Spent Fuel Pool (Completion of installation of steel support pillars) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about R/B, Unit 4, Fukushima Daiichi Nuclear Power Station Installation work of supporting structure at the bottom of Spent Fuel Pool (Completion of installation of steel support pillars)
Result of nuclide analysis of spent fuel pool water of Unit 1 Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Result of nuclide analysis of spent fuel pool water of Unit 1 Fukushima Daiichi Nuclear Power Station
Spent Fuel Pool in Reactor Building (5th floor) , Unit 4, Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Spent Fuel Pool in Reactor Building (5th floor) , Unit 4, Fukushima Daiichi Nuclear Power Station