Report on the Measures against water leakage from the Accumulated Water Transfer Pipeline in Unit 4 Turbine Building at Fukushima Daiichi Nuclear Power Station to the Nuclear and Industrial Safety Agency (NISA) of the Ministry of Economy, Trade and Indust Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Report on the Measures against water leakage from the Accumulated Water Transfer Pipeline in Unit 4 Turbine Building at Fukushima Daiichi Nuclear Power Station to the Nuclear and Industrial Safety Agency (NISA) of the Ministry of Economy, Trade and Indust
Appendix; Regarding response to water leakage near Emergency High-ground Reactor Water Injection Pump in Fukushima Daiichi Nuclear Power Station, Tokyo Electric Power Co., Inc. (Direction) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Appendix; Regarding response to water leakage near Emergency High-ground Reactor Water Injection Pump in Fukushima Daiichi Nuclear Power Station, Tokyo Electric Power Co., Inc. (Direction)
Inspection status of Trench, etc. at Fukushima Daiichi Nuclear Power Station (Preliminary Result, January 1 13, 2012) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Inspection status of Trench, etc. at Fukushima Daiichi Nuclear Power Station (Preliminary Result, January 1 13, 2012)
Scenery of obstacle removal by crane barge at intake cannel of Unit 1 to 4 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Scenery of obstacle removal by crane barge at intake cannel of Unit 1 to 4
Main Exhaust Stuck of Unit 1/2 [pictured on July 31, 2011] Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Main Exhaust Stuck of Unit 1/2 [pictured on July 31, 2011]
Bottom of Main Exhaust Stuck of Unit 1/2 Connection of emergency gas treatment piping arrangement [pictured on August 1, 2011] Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Bottom of Main Exhaust Stuck of Unit 1/2 Connection of emergency gas treatment piping arrangement [pictured on August 1, 2011]
Water leakage from Temporary Tank at east side of Unit 2 T/B (Temporary Tank at east side of Unit 2 T/B) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Water leakage from Temporary Tank at east side of Unit 2 T/B (Temporary Tank at east side of Unit 2 T/B)
Report on the Accumulated Water found at Unit 3 Radiation Waste Underground Storage Facility Building At Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Report on the Accumulated Water found at Unit 3 Radiation Waste Underground Storage Facility Building At Fukushima Daiichi Nuclear Power Station
Accumulated water in the trench between Process Main Building and Miscellaneous Solid Waste Volume Reduction Treatment Building (High Temperature Incinerator Building) in the Centralized Radiation Waste Treatment Facility at Fukushima Daiichi Nuclear Powe Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Accumulated water in the trench between Process Main Building and Miscellaneous Solid Waste Volume Reduction Treatment Building (High Temperature Incinerator Building) in the Centralized Radiation Waste Treatment Facility at Fukushima Daiichi Nuclear Powe
Result of review at the "review meeting on occupational/non-occupational ionizing radiation disease" and approval as occupational disease/injury Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Result of review at the "review meeting on occupational/non-occupational ionizing radiation disease" and approval as occupational disease/injury