Process Main Building ; Elevator room (1F) Before block [pictured on July 22, 2011] Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Process Main Building ; Elevator room (1F) Before block [pictured on July 22, 2011]
Nuclides analysis result of aerial radioactive substances at openings of the building, Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Nuclides analysis result of aerial radioactive substances at openings of the building, Fukushima Daiichi Nuclear Power Station
Primary Containment Vessel of Unit 2 of Fukushima Daiichi Nuclear Power Station Sampling Result of the Gas Control System Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Primary Containment Vessel of Unit 2 of Fukushima Daiichi Nuclear Power Station Sampling Result of the Gas Control System
Results of the sixth soundness inspection of Unit 4 reactor building at Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Results of the sixth soundness inspection of Unit 4 reactor building at Fukushima Daiichi Nuclear Power Station
Results of dust sampling at the opening of Reactor Building by T-Hawk Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Results of dust sampling at the opening of Reactor Building by T-Hawk
Attachment; Regarding Detection of Xe-135 from the PCV of Unit 2 at Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Attachment; Regarding Detection of Xe-135 from the PCV of Unit 2 at Fukushima Daiichi Nuclear Power Station
Nuclides analysis result of the radioactive materials in the air at the opening of buildings at Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Nuclides analysis result of the radioactive materials in the air at the opening of buildings at Fukushima Daiichi Nuclear Power Station
Fracture found on steel members (Diagonal bracings) in the intermediate section of the exhaust stack for Units 1 and 2 at Fukushima Daiichi NPS Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Fracture found on steel members (Diagonal bracings) in the intermediate section of the exhaust stack for Units 1 and 2 at Fukushima Daiichi NPS
Suspension of ventilation facilities heading toward dismantlement of the reactor building cover of Unit 1, at Fukushima Daiichi NPS Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Suspension of ventilation facilities heading toward dismantlement of the reactor building cover of Unit 1, at Fukushima Daiichi NPS
3-1. Current Status of Fukushima Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about 3-1. Current Status of Fukushima Fukushima Daiichi Nuclear Power Station