Usage of the port of Fukushima Daiichi Nuclear Power Station (Necessity of marine transportation) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Usage of the port of Fukushima Daiichi Nuclear Power Station (Necessity of marine transportation)
Transportation of a dry storage cask from the cask storage building to the common pool building at Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Transportation of a dry storage cask from the cask storage building to the common pool building at Fukushima Daiichi Nuclear Power Station
Inside investigation of the reactor well, the RPV and the spent fuel pool of Unit 4 at Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Inside investigation of the reactor well, the RPV and the spent fuel pool of Unit 4 at Fukushima Daiichi Nuclear Power Station
Suspension of the second cesium adsorption apparatus (SARRY) at Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Suspension of the second cesium adsorption apparatus (SARRY) at Fukushima Daiichi Nuclear Power Station
Layout of sub-drains around Fukushima Daiichi NPS Units 1-6 and central radioactive waste treatment facility (Central environment facility) Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Layout of sub-drains around Fukushima Daiichi NPS Units 1-6 and central radioactive waste treatment facility (Central environment facility)
Cause of and measures against leakage from contaminated water treatment facility's desalination system (Reverse osmosis membrane system) RO-3 at Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Cause of and measures against leakage from contaminated water treatment facility's desalination system (Reverse osmosis membrane system) RO-3 at Fukushima Daiichi Nuclear Power Station
Foundation concrete placing work started at the miscellaneous solid waste volume reduction treatment building Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Foundation concrete placing work started at the miscellaneous solid waste volume reduction treatment building
Work of filling dry storage casks (11 newly introduced casks) and transporting casks / cause of and measures against false alarm occurrence in dry cask temporary storage facility Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Work of filling dry storage casks (11 newly introduced casks) and transporting casks / cause of and measures against false alarm occurrence in dry cask temporary storage facility
Removal of obstacles including debris, etc., at the southwest side on the first floor of Unit 3 reactor building at Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Removal of obstacles including debris, etc., at the southwest side on the first floor of Unit 3 reactor building at Fukushima Daiichi Nuclear Power Station
Launch of debris removal and transfer of equipments inside the reactor well, reactor pressure vessel, and spent fuel pool of Unit 4 at Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Launch of debris removal and transfer of equipments inside the reactor well, reactor pressure vessel, and spent fuel pool of Unit 4 at Fukushima Daiichi Nuclear Power Station