The status of the 4th floor in the Reactor Building of Unit 4 Floor pushed down [pictured on November 8, 2011] Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about The status of the 4th floor in the Reactor Building of Unit 4 Floor pushed down [pictured on November 8, 2011]
The status of the 4th floor in the Reactor Building of Unit 4 Rubbles from air-conditioning ducts [pictured on November 8, 2011] Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about The status of the 4th floor in the Reactor Building of Unit 4 Rubbles from air-conditioning ducts [pictured on November 8, 2011]
The status of the 4th floor in the Reactor Building of Unit 4 Rubbles from air-conditioning ducts [pictured on November 8, 2011] Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about The status of the 4th floor in the Reactor Building of Unit 4 Rubbles from air-conditioning ducts [pictured on November 8, 2011]
The status of the 5th floor in the Reactor Building of Unit 4 Wire mesh, inlet of the air-conditioning at Spent Fuel Pool was bent to the reverse direction [pictured on November 8, 2011] Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about The status of the 5th floor in the Reactor Building of Unit 4 Wire mesh, inlet of the air-conditioning at Spent Fuel Pool was bent to the reverse direction [pictured on November 8, 2011]
Removal of debris around Fukushima Daiichi Nuclear Power Station Unit 3,4 Reactor Building (2) [pictured on January 10, 2012] Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Removal of debris around Fukushima Daiichi Nuclear Power Station Unit 3,4 Reactor Building (2) [pictured on January 10, 2012]
Removal of debris around Fukushima Daiichi Nuclear Power Station Unit 3,4 Reactor Building (1) [pictured on January 10, 2012] Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Removal of debris around Fukushima Daiichi Nuclear Power Station Unit 3,4 Reactor Building (1) [pictured on January 10, 2012]
Movies taken from T-Hawk, Reactor Building, Unit 1, 3,4 Fukushima Daiichi Nuclear Power Station Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Movies taken from T-Hawk, Reactor Building, Unit 1, 3,4 Fukushima Daiichi Nuclear Power Station
Confirmation of the reactor well on the fifth floor of Nuclear Reactor Building Unit 4 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Confirmation of the reactor well on the fifth floor of Nuclear Reactor Building Unit 4
Confirmation of the spend fuel pool on the fifth floor of Nuclear Reactor Building Unit 4 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Confirmation of the spend fuel pool on the fifth floor of Nuclear Reactor Building Unit 4
Confirmation of support structure installed at the bottom of the spend fuel pool on the second floor of Nuclear Reactor Building Unit 4 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Confirmation of support structure installed at the bottom of the spend fuel pool on the second floor of Nuclear Reactor Building Unit 4