Reactor coolant purification system purge line connected with a temporary hose (Enlarged image) Photo taken on July 6, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Reactor coolant purification system purge line connected with a temporary hose (Enlarged image) Photo taken on July 6, 2012
Reactor coolant purification system purge line connected with a temporary hose Photo taken on July 6, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Reactor coolant purification system purge line connected with a temporary hose Photo taken on July 6, 2012
Functional check after the generator installation (Vibration measurement during trial operation) [Permanent installation completed on October 11, 2012] Photo taken on October 11, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Functional check after the generator installation (Vibration measurement during trial operation) [Permanent installation completed on October 11, 2012] Photo taken on October 11, 2012
Power panel (P/C 2D-2) installation completed on October 29, 2012 Photo taken on October 29, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Power panel (P/C 2D-2) installation completed on October 29, 2012 Photo taken on October 29, 2012
Power panel being carried in Photo taken on October 16, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Power panel being carried in Photo taken on October 16, 2012
Power panel being lifted up by a crane car Photo taken on October 16, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Power panel being lifted up by a crane car Photo taken on October 16, 2012
Generator of the residual heat removal system (C system) [Functional check completed on October 22, 2012] Photo taken on October 29, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Generator of the residual heat removal system (C system) [Functional check completed on October 22, 2012] Photo taken on October 29, 2012
Generator rotor being carried into the building [Carry-in completed on October 18, 2012] Photo taken on October 18, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Generator rotor being carried into the building [Carry-in completed on October 18, 2012] Photo taken on October 18, 2012
Generator rotor being lifted up by a crane car Photo taken on October 18, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Generator rotor being lifted up by a crane car Photo taken on October 18, 2012
Generator stator being carried into the building [Carry-in completed on October 15, 2012] Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Generator stator being carried into the building [Carry-in completed on October 15, 2012]