Generator stator being lifted up by a crane car Photo taken on October 15, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Generator stator being lifted up by a crane car Photo taken on October 15, 2012
Control panel installation (Completed on October 1, 2012) Photo taken on October 19, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Control panel installation (Completed on October 1, 2012) Photo taken on October 19, 2012
Functional check (Completed on October 29, 2012) Photo taken on October 29, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Functional check (Completed on October 29, 2012) Photo taken on October 29, 2012
Power panel (M/C 1HPCS) being carried into the building (Carry-in completed on October 24) Photo taken on October 24, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Power panel (M/C 1HPCS) being carried into the building (Carry-in completed on October 24) Photo taken on October 24, 2012
Power panel being carried into the building Photo taken on October 24, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Power panel being carried into the building Photo taken on October 24, 2012
Power panel being lifted up by a crane car Photo taken on October 24, 2012 Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Power panel being lifted up by a crane car Photo taken on October 24, 2012
Description of Changes to the Report on Facility Management Plan for Units 1-4 of Fukushima Daiichi Nuclear Power Station Based on the "Policy on the Mid-term Security" Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Description of Changes to the Report on Facility Management Plan for Units 1-4 of Fukushima Daiichi Nuclear Power Station Based on the "Policy on the Mid-term Security"
Leakage Condition Photo [taken on November 20, 2012] Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Leakage Condition Photo [taken on November 20, 2012]
Vent line [photo taken on November 20, 2012] Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Vent line [photo taken on November 20, 2012]
Water leakage from the Second Cesium Absorption Apparatus (SARRY) Vent Line Submitted by Fukushima Nucl… on Fri, 12/04/2020 - 10:12 Read more about Water leakage from the Second Cesium Absorption Apparatus (SARRY) Vent Line